CentriQS lets users identify tasks at risk of getting behind schedule. For example, if you planned to complete a task within 8 hours, already spent 4 hours and understand that you there are 6 hours are left, that means that this task is at risk of being delayed for 2 hours. In this case the program can start “beating the alarm”: the task icon turns yellow, task background can be highlighted, and notification can pop up/be sent by email.